Hillsborough County Public Schools Facilities
Action Item

DATE: Tuesday, September 6, 2005
TO: School Board Members
FROM: MaryEllen Elia, Superintendent

SUBJECT / RECOMMENDATIONS

MILES ELEMENTARY SCHOOL - REROOFING
APPROVAL OF CHANGE ORDER NO. 3 - $3,805.93 EXTRA
ACCEPTANCE OF PROJECT

EXECUTIVE SUMMARY

This project was planned by the architectural firm of Smith & Company Architects. Horus Construction Services provided construction management services under their continuing services agreement. The scope of work provided for roof replacement.

This change order provides for the final reconciliation of the Direct Purchase Program.

The architect advises that the referenced project is finally complete in accordance with the plans and specifications and other contract documents and recommends Board acceptance.

ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)

Critical Success Factor 6.a.8 - Provide sufficient student stations to ensure uninterrupted student learning and data gathering as measured by District Operational Goals plan.

FINANCIAL IMPACT (Budgeted: Yes)

This item is included in the District Capital Outlay: Public Education Capital Outlay (PECO) Maintenance.
Contract Status:
Guaranteed Maximum Price: $592,583.00
Change Orders Previously Approved: $200,375.37 Credit
Change Order Recommended Herein: $3,805.93 Extra
Revised Guaranteed Maximum Price: $396,013.56
Payments to Date: $391,707.63
Balance Due: $4,305.93
Contract Completion Date: September 2, 2004
Substantial Completion Date: September 2, 2004

EVALUATION

SUBMITTED BY:

J. Thomas Blackwell
General Manager of Construction
(813) 272-4112
Cathy L. Valdes
Chief Facilities Officer
(813) 272-4004
6.14
Hillsborough County Public Schools (Florida) * Mtg.#20050906_151 * Section E Item# 6.14