Hillsborough County Public Schools Facilities
Action Item

DATE: Tuesday, November 22, 2005
TO: School Board Members
FROM: MaryEllen Elia, Superintendent

SUBJECT / RECOMMENDATIONS

APARICIO-LEVY ADULT TECHNICAL CENTER
NEW FACILITY
APPROVAL OF CHANGE ORDER NO. 2 - $737,745.54 CREDIT

EXECUTIVE SUMMARY

This project was planned by the architectural firm of Hellmuth, Obata + Kassabaum, Inc. On March 12, 2002, the Board appointed the construction management firm of Peter R. Brown Construction, Inc. The scope of work provides for the construction of a new adult training facility to service the District and the community.

This change order provides credits for the return of unused contingency funds and the final reconciliation of the Direct Purchase and Owner Controlled Insurance Programs.

ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)

Critical Success Factor 6.a.8 - Provide sufficient student stations to ensure uninterrupted student learning and data gathering as measured by District Operational Goals plan.

FINANCIAL IMPACT (Budgeted: Yes)

This item is included in the District Capital Outlay: Community Investment Tax.

Contract Status:
Guaranteed Maximum Price: $3,550,000.00
Change Order Previously Approved: $85,723.75 Extra
Change Order Recommended Herein: $737,745.54 Credit
Revised Guaranteed Maximum Price: $2,897,978.21

Contract Completion Date: May 30, 2005

EVALUATION

SUBMITTED BY:

J. Thomas Blackwell
General Manager of Construction
(813) 272-4112
Cathy L. Valdes
Chief Facilities Officer
(813) 272-4004
6.05
Hillsborough County Public Schools (Florida) * Mtg.#20051122_161 * Section E Item# 6.05