Facilities Action Item |
DATE: Tuesday, November 22, 2005
TO: School Board Members
FROM: MaryEllen Elia, Superintendent
SUBJECT / RECOMMENDATIONS
EXECUTIVE SUMMARY
This project was planned by the architectural firm of Alfonso Architects. On March 12, 2002, the Board appointed the construction management firm of J.O. DeLotto & Sons, Inc. The scope of work includes construction of a new K-8 school to house 1226 students.
This change order provides for modification of two classrooms into a single room for use as a dance studio.
ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)
Critical Success Factor 6.a.8 – Provide sufficient student stations to ensure uninterrupted student learning and data gathering as measured by District Operational Goals plan.
FINANCIAL IMPACT (Budgeted: Yes)
This item is included in the District Capital Outlay: Certificates of Participation Series 2003 and Community Investment Tax.
Contract Status:
Guaranteed Maximum Price: $11,277,514.00
Change Orders Previously Approved: $1,316,334.72 Credit
Change Order Recommended Herein: $34,757.00 Extra
Revised Guaranteed Maximum Price: $9,995,936.28
Contract Completion Date: May 6, 2005
Time Extension Previously Approved: 21 calendar days
Revised Completion Date: May 27, 2005
EVALUATION
SUBMITTED BY:
J. Thomas Blackwell
General Manager of Construction (813) 272-4112 |
Cathy L. Valdes
Chief Facilities Officer (813) 272-4004 |
6.09 | |