Hillsborough County Public Schools Facilities
Action Item

DATE: Tuesday, February 7, 2006
TO: School Board Members
FROM: MaryEllen Elia, Superintendent

SUBJECT / RECOMMENDATIONS

FRANKLIN MIDDLE SCHOOL
RENOVATIONS AND GYMNASIUM ADDITION
APPROVAL OF CHANGE ORDER NO. 11 - $197,018.38 CREDIT

EXECUTIVE SUMMARY

This project was planned by the architectural firm of Howard and Associates, Architects, PA. On March 12, 2002, the Board appointed the construction management firm of The Morganti Group. The scope of work includes the addition of a new gymnasium and elevator. Also included is the renovation of existing classrooms, administration offices, and the auditorium to accommodate the new magnet program.

This change order provides a credit for the direct purchase of materials by the District.

ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)

Critical Success Factor 6.a.8 - Provide sufficient student stations to ensure uninterrupted student learning and data gathering as measured by District Operational Goals plan.

FINANCIAL IMPACT (Budgeted: Yes)

This item is included in the District Capital Outlay: Community Investment Tax and 2 Mill.
Contract Status:
Guaranteed Maximum Price: $4,600,000.00
Change Orders Previously Approved: $2,763,979.45
Change Order Recommended Herein: $197,018.38 Credit
Revised Guaranteed Maximum Price: $7,166,961.07

Original Completion Date: September 1, 2004
Time Extensions Previously Approved: 332 Calendar Days
Revised Completion Date: July 30, 2005

EVALUATION

N/A

SUBMITTED BY:

J. Thomas Blackwell
General Manager of Construction
(813) 272-4112
Cathy L. Valdes
Chief Facilities Officer
(813) 272-4004
6.13