This project was planned by the engineering firm of Carastro & Associates, Inc. On July 12, 2005, the Board appointed Becker Communications, Inc. to provide construction management services. The scope of work provides for fire alarm and intercom replacement.
Change Order No. 1 provides for additional intercom cables in the Media Center. Change Order No. 2 provides for revisions to the fire alarm system, new clock for Room 100F, and two weatherproof intercom speakers at front of Administration Building.
ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)
Critical Success Factor 6.a.8 - Provide sufficient student stations to ensure uninterrupted student learning and data gathering as measured by District Operational Goals plan.
FINANCIAL IMPACT (Budgeted: Yes)
This item is included in the District Capital Outlay: 2 Mill and Public Education Capital Outlay (PECO) Maintenance.
Contract Status:
Guaranteed Maximum Price: $126,905.00
Change Order No. 1 Recommended Herein: $6,670.00 Extra
Change Order No. 2 Recommended Herein: $5,685.00 Extra
Revised Guaranteed Maximum Price: $139,260.00
Contract Completion Date: October 20, 2005
EVALUATION
SUBMITTED BY:
J. Thomas Blackwell
General Manager of Construction (813) 272-4112 |
Cathy L. Valdes
Chief Facilities Officer (813) 272-4004 |
6.20 | |
Hillsborough County Public Schools (Florida) * Mtg.#20060207_168 * Section E Item# 6.20 |