Facilities Action Item |
DATE: Tuesday, February 7, 2006
TO: School Board Members
FROM: MaryEllen Elia, Superintendent
SUBJECT / RECOMMENDATIONS
EXECUTIVE SUMMARY
This project was planned by the architectural firm of Rowe Architects, Inc. On November 9, 2004, the Board appointed the construction management firm of Creative Contractors, Inc. The scope of work provides for new finishes throughout the facility, new roof at all the buildings with the exception of the Media Center, new covered walkways and fire alarm, intercom, telephone, data, security, HVAC, electrical, and lighting systems. It also provides for the removal of existing suspended classroom ceilings, replacement of windows in the cafeteria, and ADA accessibility at classroom entrances and toilets.
Change Order No. 1 provides for roofing and window modifications. It also provides a credit for deleted signs. Change Order No. 2 provides a credit for the direct purchase of materials by the District.
ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)
Critical Success Factor 6.a.8 - Provide sufficient student stations to ensure uninterrupted student learning and data gathering as measured by District Operational Goals plan.
FINANCIAL IMPACT (Budgeted: Yes)
EVALUATION
SUBMITTED BY:
J. Thomas Blackwell
General Manager of Construction (813) 272-4112 |
Cathy L. Valdes
Chief Facilities Officer (813) 272-4004 |
6.18 | |
Hillsborough County Public Schools (Florida) * Mtg.#20060207_168 * Section E Item# 6.18 |