SYMMES ELEMENTARY SCHOOL
DEMOLITION AND RECONSTRUCTION
APPROVAL OF CHANGE ORDER NO. 1 - $622,914.38 CREDIT
APPROVAL OF CHANGE ORDER NO. 2 - $10,313.00 NET EXTRA

EXECUTIVE SUMMARY

Symmes Elementary School was designed and constructed by the team of Portela & Associates and Beers Construction Company, now owned by Skanska USA Building, Inc. Over the last four and one-half years, the school has experienced unusual cracking of the walls and floors. On October 20, 2003, the School Board entered into a tolling agreement with the architect, construction manager and geotechnical consultant. A tolling agreement stops the running of the statutory period allowed for establishing possible claims and the parties are allowed additional time to consider the issues and work toward a resolution. Subsequent investigations have revealed unsuitable soils remained beneath the failed structures. Testing is complete and it has been determined that Buildings 2 and 3 will need to be demolished and reconstructed. Legal issues are being addressed to assign financial responsibility to accountable parties. On May 3, 2005, the Board appointed Cooper Johnson Smith Architects, Inc. and Batson-Cook Company to provide design and construction management services. The scope of work includes a new classroom building and media center. The Frost Elementary School prototype design will be used for these replacement facilities.

Change Order No. 1 provides a credit for the direct purchase of materials by the District. Change Order No. 2 provides for additional sidewalk, elevator keys, exterior wall at stair, roof drains at canopies, and building foundation renovations. It also provides for deletion of ceramic tile at handicapped bathtub.

ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)

Critical Success Factor 6.a.8 - Provide sufficient student stations to ensure uninterrupted student learning and data gathering as measured by District Operational Goals plan.

FINANCIAL IMPACT (Budgeted: Yes)

This item is included in the District Capital Outlay: 2 Mill.
Contract Status:
Guaranteed Maximum Price: $4,235,572.00
Change Order No. 1 Recommended Herein: $622,914.38 Credit
Change Order No. 2 Recommended Herein: $18,226.00 Extra and $7,913.00 Credit
Revised Guaranteed Maximum Price: $3,622,970.62
Contract Completion Date: June 28, 2006

EVALUATION

SUBMITTED BY:

J. Thomas Blackwell
General Manager of Construction
(813) 272-4112
Cathy L. Valdes
Chief Facilities Officer
(813) 272-4004
6.19
Hillsborough County Public Schools (Florida) * Mtg.#20060502_175 * Section E Item# 6.19