APPROVAL OF CHANGE ORDER NO. 12 - $277,683.79 NET CREDIT

EXECUTIVE SUMMARY

This project was planned by the architectural firm of Long & Associates Engineers/Architects. On May 7, 2002, the Board appointed the construction management firm of Hardin Construction Group. This new facility was constructed to relieve overcrowding at Eisenhower Middle School.

This change order provides credits for the return of unused contingency funds and fencing allowance, and deletion of an exterior water cooler. It also provides for a new 5' wide concrete sidewalk for handicapped access from the classroom buildings to the playcourts.

ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)

Critical Success Factor 6.a.8 - Provide sufficient student stations to ensure uninterrupted student learning and data gathering as measured by District Operational Goals plan.

FINANCIAL IMPACT (Budgeted: Yes)

This item is included in the District Capital Outlay: Community Investment Tax.
Contract Status:
Guaranteed Maximum Price: $14,146,128.00
Change Orders Previously Approved: $3,388,902.96 Credit
Change Order Recommended Herein: $281,702.79 Credit and $4,019.00 Extra
Revised Guaranteed Maximum Price: $10,479,541.25
Revised Construction Cost: $13,751,584.12
Contract Completion Date: June 8, 2004

EVALUATION

SUBMITTED BY:

J. Thomas Blackwell
General Manager of Construction
(813) 272-4112
Cathy L. Valdes
Chief Facilities Officer
(813) 272-4004
6.10
Hillsborough County Public Schools (Florida) * Mtg.#20060711_179 * Section E Item# 6.10