JUST ELEMENTARY SCHOOL - DEMOLITION & REPLACEMENT /STEWART MIDDLE SCHOOL - CLASSROOM ADDITION, TECHNOLOGY LAB DEMOLITION AND REPLACEMENT
APPROVAL OF CHANGE ORDER NO. 5 (STEWART): $60,177.00 CREDIT

EXECUTIVE SUMMARY

These projects were planned by The Architectural Practice. On March 12, 2002, the Board appointed the construction management firm of Rodda Construction. A preplanning evaluation determined that the Just Elementary facility could not be renovated in a cost-effective manner. Existing buildings were demolished with the exception of the recently constructed Media Center. A new elementary school to house approximately 576 students was constructed on the site. The existing Stewart Technology Lab was demolished and a replacement lab was constructed to allow the Just multipurpose dining room to be attached to the existing Stewart kitchen which was remodeled to accommodate both schools. A 14 classroom addition to house 308 students at Stewart was constructed. The full-service school components will be relocated on campus to provide better accessibility to the public.

This change order provides for correction of a previous error on Change Order 4. Construction Change Directive 44R was inadvertently included in both Change Orders 3 and 4, and should have only been included in Change Order 3.

ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)

Critical Success Factor 6.a.8 - Provide sufficient student stations to ensure uninterrupted student learning and data gathering as measured by District Operational Goals plan.

FINANCIAL IMPACT (Budgeted: Yes)

These items are included in the District Capital Outlay: Stewart Elementary is funded by Certificates of Participation Series 2002.
Stewart Middle School
Contract Status:

Guaranteed Maximum Price: $2,451,490.00
Change Orders Previously Approved: $166,923.53 Credit
Change Order Recommended Herein: $60,177.00 Credit
Revised Guaranteed Maximum Price: $2,224,389.47
Contract Completion Date: September 14,2004
Approved Time Extension: 75 Calendar days
Revised Completion Date: November 28, 2004

EVALUATION

SUBMITTED BY:

Thomas Blackwell
General Manager of Construction
272-4115
MaryEllen Elia
Chief Facilities Officer
272-4004
6.05
Hillsborough County Public Schools (Florida) * Mtg.#20050517_142 * Section E Item# 6.05