Hillsborough County Public Schools Facilities
Action Item

DATE: Thursday, September 7, 2006
TO: School Board Members
FROM: MaryEllen Elia, Superintendent

SUBJECT / RECOMMENDATIONS

SIMMONS CAREER CENTER
NEW FACILITY
ACCEPTANCE OF PROJECT

EXECUTIVE SUMMARY

This project was planned by the architectural firm of Long & Associates, Inc. On March 12, 2002, the Board appointed the construction management firm of Christiano Construction Company, Inc.

The architect advises that the referenced project is finally complete in accordance with the plans and specifications and other contract documents and recommends Board acceptance.

ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)

Goal 6 - All schools in the district will be assigned a state grade of A, B, or C.

FINANCIAL IMPACT (Budgeted: Yes)

This item was included in the District Capital Outlay: Certificates of Participation Series 2001.
Contract Status:
Guaranteed Maximum Price: $5,448,174.00
Change Orders Previously Approved: $907,429.09 Credit
Revised Guaranteed Maximum Price: $4,540,744.91
Payments to Date: $4,467,766.67
Balance Due: $72,978.24
Revised Construction Cost: $5,296,738.74

Original Completion Date: July 14, 2004
Time Extension Previously Approved: 70 calendar days
Revised Completion Date: September 22, 2004
Substantial Completion Date: July 14, 2004

EVALUATION

SUBMITTED BY:

J. Thomas Blackwell
General Manager of Construction
(813) 272-4112
Cathy L. Valdes
Chief Facilities Officer
(813) 272-4004
6.13
Hillsborough County Public Schools (Florida) * Mtg.#20060907_183 * Section E Item# 6.13