Facilities Action Item |
DATE: Thursday, September 7, 2006
TO: School Board Members
FROM: MaryEllen Elia, Superintendent
SUBJECT / RECOMMENDATIONS
EXECUTIVE SUMMARY
On March 8, 2005, the Board appointed Ruyle Hayes + Jennewein Architects P.A. and Construct Two Construction Managers, Inc. to provide design and construction management services for the addition of a gymnasium at Sligh Middle School.
This change order provides a credit for the direct purchase of materials by the District.
ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)
Goal 6 - All schools in the district will be assigned a state grade of A, B, or C.
FINANCIAL IMPACT (Budgeted: Yes)
This item is included in the District Capital Outlay: Certificates of Participation Series 2001B and 2 Mill.
Contract Status:
Guaranteed Maximum Price: $1,941,041.00
Change Order Recommended Herein: $231,050.18 Credit
Revised Guaranteed Maximum Price: $1,709,990.82
Revised Construction Cost: $1,927,632.50
Contract Completion Date: December 24, 2006
EVALUATION
SUBMITTED BY:
J. Thomas Blackwell
General Manager of Construction (813) 272-4112 |
Cathy L. Valdes
Chief Facilities Officer (813) 272-4004 |