Hillsborough County Public Schools Facilities
Action Item

DATE: Tuesday, September 26, 2006
TO: School Board Members
FROM: MaryEllen Elia, Superintendent

SUBJECT / RECOMMENDATIONS

CITRUS PARK ELEMENTARY SCHOOL
CLASSROOMS FOR KIDS ADDITION
APPROVAL OF CHANGE ORDER NO. 2 - $247,624.40 NET CREDIT

EXECUTIVE SUMMARY

This project was planned by the architectural firm of Gottfried + Garcia Architects, AIA, PA. On January 13, 2004, the Board appointed the construction management firm of SL Construction & Remodeling, Inc. On October 19, 2004, a joint venture between SL Construction & Remodeling and Manhattan Construction Company was approved to ensure the availability of sufficient resources to meet all project requirements. The scope of work provides for ten additional classrooms that meet class size reduction requirements.

This change order provides a credit for deletion of site wall north of Building 1 and final reconciliation of the Direct Purchase Program. It also provides for window revisions at Building 1.

ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)

Goal 6 - All schools in the district will be assigned a state grade of A, B, or C.

FINANCIAL IMPACT (Budgeted: Yes)

This item is included in the District Capital Outlay: Classrooms for Kids.
Contract Status:
Guaranteed Maximum Price: $1,290,337.00
Change Order Previously Approved: $16,631.38 Extra
Change Order Recommended Herein: $251,549.40 Credit and $3,925.00 Extra
Revised Guaranteed Maximum Price: $1,059,343.98
Revised Construction Cost: $1,294,088.56

Contract Completion Date: February 16, 2006

EVALUATION

SUBMITTED BY:

J. Thomas Blackwell
General Manager of Construction
(813) 272-4112
Cathy L. Valdes
Chief Facilities Officer
(813) 272-4004
6.09
Hillsborough County Public Schools (Florida) * Mtg.#20060926_184 * Section E Item# 6.09