VARIOUS SCHOOLS
CLASSROOMS FOR KIDS (PACKAGE 6)
APPROVAL OF CHANGE ORDER NO. 4 - $1,196,257.00 CREDIT
APPROVAL OF CHANGE ORDER NO. 5 - $20,511.00 EXTRA
APPROVAL OF CHANGE ORDER NO. 6 - $139,166.00 EXTRA

EXECUTIVE SUMMARY

On September 7, 2004, the Board appointed Schenkel Shultz Architecture and Turner Construction to provide design and construction management services for classroom additions at Boyette Springs, Cimino, Kingswood, Riverview and Ruskin Elementary Schools. These additions are necessary to meet class size reduction requirements. The scope of work provides for the construction of 16 additional classrooms at Boyette Springs, Cimino, and Ruskin Elementary Schools, and 10 additional classrooms at Kingswood and Riverview Elementary Schools.

Change Order No. 4 provides for the direct purchase of materials by the District. Change Order No. 5 provides for additional electrical service at Cimino Elementary School as required by Tampa Electric Company. Change Order No. 6 provides for additional storm water drainage work at Ruskin and Riverview Elementary Schools as required by the Southwest Florida Water Mangement District.

ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)

Goal 6 - All schools in the district will be assigned a state grade of A, B, or C.

FINANCIAL IMPACT (Budgeted: Yes)

These items are included in the District Capital Outlay: Classrooms for Kids (Boyette Springs, Cimino, Riverview, and Ruskin Elementary Schools) and Certificates of Participation Series 2001 (Kingswood Elementary School).
Contract Status:
Guaranteed Maximum Price: $8,888,986.00
Change Orders Previously Recommended: $147,669.03 Extra
Change Order No. 4 Recommended Herein: $1,196,257.00 Credit
Change Order No. 5 Recommended Herein: $20,511.00 Extra
Change Order No. 6 Recommended Herein: $139,166.00 Extra
Revised Guaranteed Maximum Price: $8,000,075.03
Revised Construction Cost: $9,128,562.16
Original Completion Date: May 11, 2006
Time Extension Previously Approved: 3 calendar days
Revised Completion Date: May 14, 2006

EVALUATION

SUBMITTED BY:

J. Thomas Blackwell
General Manager of Construction
(813) 272-4112
Cathy L. Valdes
Chief Facilities Officer
(813) 272-4004
6.14