Hillsborough County Public Schools Facilities
Action Item

DATE: Tuesday, October 24, 2006
TO: School Board Members
FROM: MaryEllen Elia, Superintendent

SUBJECT / RECOMMENDATIONS

TURNER ELEMENTARY SCHOOL
NEW FACILITY
APPROVAL OF CHANGE ORDER NO. 12 - $2,122.00 EXTRA

EXECUTIVE SUMMARY

This project was planned by the architectural firm of Woodroffe Corporation Architects. On November 18, 2003, the Board appointed the construction management firm of Hardin Construction. This new facility was a reuse of the Chiles Elementary School design and opened in August 2005. Relief was provided for Clark, Heritage, and Pride Elementary Schools.

This change order provides lay-in acoustical tile ceilings in storage rooms.

ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)

Goal 6 - All schools in the district will be assigned a state grade of A, B, or C.

FINANCIAL IMPACT (Budgeted: Yes)

This item is included in the District Capital Outlay: Certificates of Participation Series 2002.

Contract Status:
Guaranteed Maximum Price: $9,237,017.00
Change Orders Previously Approved: $1,624,751.20 Credit
Change Order Recommended Herein: $2,122.00 Extra
Revised Guaranteed Maximum Price: $7,614,387.80
Revised Construction Cost: $10,201,009.85

Original Completion Date: July 31, 2005
Time Extension Previously Approved: 137 calendar days
Revised Completion Date: December 15, 2005

EVALUATION

SUBMITTED BY:

J. Thomas Blackwell
General Manager of Construction
(813) 272-4112
Cathy L. Valdes
Chief Facilities Officer
(813) 272-4004
6.11
Hillsborough County Public Schools (Florida) * Mtg.#20061024_186 * Section E Item# 6.11