Hillsborough County Public Schools Facilities
Action Item

DATE: Tuesday, November 21, 2006
TO: School Board Members
FROM: MaryEllen Elia, Superintendent

SUBJECT / RECOMMENDATIONS

B.T. WASHINGTON SCHOOL
ADDITION AND RENOVATION
ACCEPTANCE OF PROJECT

EXECUTIVE SUMMARY

This project was planned by the architectural firm of Rick Z. Smith & Associates Architects, Inc. On March 12, 2002, the Board appointed the construction management firm of R.J. Bunbury Company, Inc. The scope of work for the conversion of B.T. Washington from a middle school to K-8 was as follows: the existing parking lots were modified, resurfaced, and re-striped to better accommodate the elementary and middle school programs. Areas of poor drainage, missing gutters and downspouts were corrected. Buildings 1, 2, and 3 were remodeled for better utilization and to meet current code requirements. There was an addition of a Science lab and two Science classrooms. Building 4 was demolished and a new building was constructed to house 8 classrooms. Existing main electrical service, fire alarm, security, intercom, telephone and data systems, lighting, casework, teaching aids, and ceilings were replaced campus-wide. Mechanical system revisions were made to upgrade the toilet room exhausts, and replace the air handler in administration. The entire campus was painted. Floor finish replacement was handled on a room-by-room basis.

The architect advises that the referenced project is finally complete in accordance with the plans and specifications and other contract documents and recommends Board acceptance.

ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)

Goal 6 - All schools in the district will be assigned a state grade of A, B, or C.

FINANCIAL IMPACT (Budgeted: Yes)

This item is included in the District Capital Outlay: Community Investment Tax.
Contract Status:
Guaranteed Maximum Price: $4,062,861.00
Change Orders Previously Approved: $606,670.67 Credit
Revised Guaranteed Maximum Price: $3,456,190.33
Payments to Date: $3,359,800.80
Balance Due: $96,389.53
Revised Construction Cost: $4,436,564.56

Original Completion Date: July 25, 2004
Time Extension Previously Approved: 28 Calendar Days
Revised Completion Date: August 22, 2004
Substantial Completion Date: July 19, 2004

EVALUATION

SUBMITTED BY:

J. Thomas Blackwell
General Manager of Construction
(813) 272-4112
Cathy L. Valdes
Chief Facilities Officer
(813) 272-4004
6.09b
Hillsborough County Public Schools (Florida) * Mtg.#20061121_188 * Section E Item# 6.09b