Facilities Action Item |
DATE: Tuesday, November 21, 2006
TO: School Board Members
FROM: MaryEllen Elia, Superintendent
SUBJECT / RECOMMENDATIONS
EXECUTIVE SUMMARY
This project was planned by the engineering firm of Hahn Engineering, Inc. On March 14, 2006, the Board awarded the project to the low bidder, Air Mechanical & Service Corporation. The scope of work provides for the replacement of mechanical system components, including the chillers and air handlers.
This change order provides for a new controls system. It also provides a time extension for delayed release of direct purchased heating, ventilating, and air conditioning (HVAC) equipment.
ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)
Goal 6 - All schools in the district will be assigned a state grade of A, B, or C.
FINANCIAL IMPACT (Budgeted: Yes)
This item is included in the District Capital Outlay: 2 Mill.
Contract Status:
Contract Sum: $912,472.00
Change Order Previously Approved: $7,788.00 Extra
Change Order Recommended Herein: $50,760.00 Extra
Revised Contract Sum: $971,020.00
Revised Construction Cost: $971,020.00
Original Completion Date: August 19, 2006
Time Extension Recommended Herein: 106 Calendar Days
Revised Completion Date: December 3, 2006
EVALUATION
SUBMITTED BY:
J. Thomas Blackwell
General Manager of Construction (813) 272-4112 |