EXECUTIVE SUMMARY

This project was planned by the architectural firm of Sylla, Incorporated. On March 12, 2002, the Board appointed the construction management firm of HC Beck. This new facility relieved overcrowding at Foster and Lopez Elementary Schools.

This change order provides a credit for project savings and the return of unused contingency funds. It also provides for the final reconciliation of the Owner Controlled Insurance Program.

ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)

Critical Success Factor 6.a.8 - Provide sufficient student stations to ensure uninterrupted student learning and data gathering as measured by District Operational Goals plan.

FINANCIAL IMPACT (Budgeted: Yes)

This item is included in the District Capital Outlay: Certificates of Participation Series 1999.

Guaranteed Maximum Price: $6,822,557.00
Change Orders Previously Approved: $1,990,764.11 Credit
Change Order Recommended Herein: $224,717.62 Credit and $115,104.32 Extra
Revised Guaranteed Maximum Price: $4,722,179.59

Contract Completion Date: August 13, 2004

EVALUATION

SUBMITTED BY:

Thomas Blackwell
General Manager of Construction
(813) 272-4112
MaryEllen Elia
Chief Facilities Officer
(813) 272-4004
6.16
Hillsborough County Public Schools (Florida) * Mtg.#20050607_144 * Section E Item# 6.16