BOWERS-WHITLEY CAREER CENTER - NEW FACILITY
APPROVAL OF CHANGE ORDER NO. 10 - $18,847.00 EXTRA

EXECUTIVE SUMMARY

This project was planned by the architectural firm of Holmes Hepner & Associates. On February 6, 2001, the Board appointed the construction management firm of Beck, Ltd. The scope of work includes construction of a new Career Center located in the University area.

This change order provides for a turnaround driveway at the North parking lot of Muller Elementary to enable motorists on 138th Street to turn around without entering school property.

ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)

Critical Success Factor 6.a.8 - Provide sufficient student stations to ensure uninterrupted student learning and data gathering as measured by District Operational Goals plan.

FINANCIAL IMPACT (Budgeted: Yes)

This item is included in the District Capital Outlay: Community Investment Tax.

Contract Status:
Guaranteed Maximum Price: $7,307,749.00
Change Orders Previously Approved: $1,909,768.76 Credit
Change Order Recommended Herein: $18,847.00 Extra
Revised Guaranteed Maximum Price: $5,416,827.24

Original Completion Date: October 19, 2003
Time Extension Previously Approved: 108 Calendar Days
Revised Completion Date: February 4, 2004

EVALUATION

SUBMITTED BY:

Thomas Blackwell
General Manager of Construction
272-4115
MaryEllen Elia
Chief Facilities Officer
272-4004
6.03
Hillsborough County Public Schools (Florida) * Mtg.#20050517_142 * Section E Item# 6.03