This project was planned by the engineering firm of Long & Associates. The scope of work provides for furnishing and installing replacement field lighting for the baseball field at Leto High School.
The project was advertised, and three bidders responded (see attachment). Staff concurs with the engineer and recommends award to the low bidder, Himes Electric Company, Incorporated.
The project will start December 5, 2006, with a projected completion date of March 1, 2007.
ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)
Critical Success Factor 6.a.7 - Provide school facility maintenance that allows for uninterrupted student learning (proper electricity, A/C, etc.) as measured by District Operational Goals plan.
FINANCIAL IMPACT (Budgeted: Yes)
The low bid amount of $250,336 is allocated in the 2006/07 2 Mill budget.
EVALUATION
SUBMITTED BY:
Rory Salimbene
General Manager of Maintenance (813) 635-1101 |
Cathy L. Valdes
Chief Facilities Officer |
6.01b | |
Hillsborough County Public Schools (Florida) * Mtg.#20061121_188 * Section E Item# 6.01b |