LENNARD HIGH SCHOOL / NEW FACILITY
APPROVAL OF CHANGE ORDER NO. 6 - $90,000.00 EXTRA
APPROVAL OF CHANGE ORDER NO. 7 - $95,829.99 EXTRA
APPROVAL OF CHANGE ORDER NO. 8 - $46,440.37 EXTRA
APPROVAL OF CHANGE ORDER NO. 9 - $57,701.25 EXTRA
APPROVAL OF CHANGE ORDER NO. 10 - $177,287.62 CREDIT

EXECUTIVE SUMMARY

This project was planned by the architectural firm of Holmes Hepner & Associates Architects. On June 15, 2004, the Board appointed the construction management firm of The Beck Group. This new facility was a reuse of the Alonso High School design. The school opened in August 2006 and provided relief for East Bay High School and the South County area.

Change Order No. 6 provides for Construction Manager's general and excess liability insurance necessitated by the cancellation of the Owner Controlled Insurance Program. Change Order No. 7 provides revisions to the auditorium as required by the District Safety Office. Change Order No. 8 provides modifications to the entrance drives to accommodate off-site road construction. Change Order No. 9 provides for wetland mitigation. Change Order No. 10 provides for final reconciliation of the Owner Controlled Insurance Program.

ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)

Goal 6 - All schools in the district will be assigned a state grade of A, B, or C.

FINANCIAL IMPACT (Budgeted: Yes)

This item is included in the District Capital Outlay: Community Investment Tax 2004 (new facility) and Certificates of Participation Series 2004C (athletic facility).
Contract Status:
Guaranteed Maximum Price: $35,159,855.00
Change Orders Previously Approved: $10,341,303.89 Credit
Change Order No. 6 Recommended Herein: $90,000.00 Extra
Change Order No. 7 Recommended Herein: $95,829.99 Extra
Change Order No. 8 Recommended Herein: $46,440.37 Extra
Change Order No. 9 Recommended Herein: $57,701.25 Extra
Change Order No. 10 Recommended Herein: $177,287.62 Credit
Revised Guaranteed Maximum Price: $24,931,235.10
Revised Construction Cost: $34,963,420.27
Contract Completion Date: July 24, 2006

EVALUATION

SUBMITTED BY:

J. Thomas Blackwell
General Manager of Construction
(813) 272-4112
Cathy L. Valdes
Chief Facilities Officer
(813) 272-4004
6.22
Hillsborough County Public Schools (Florida) * Mtg.#20070116_228 * Section E Item# 6.22