ANCILLARY OFFICE BUILDING
NEW FACILITY
APPROVAL OF CHANGE ORDER NO. 1 - $1,082,334.57 CREDIT
APPROVAL OF CHANGE ORDER NO. 2 - $20,980.81 CREDIT
APPROVAL OF CHANGE ORDER NO. 3 - $0.00 EXTRA / 21 CALENDAR DAY TIME EXTENSION

EXECUTIVE SUMMARY

The existing Instructional Services Center had exceeded its useful life and was demolished to allow construction of a two-story 100,000 square foot office building. On March 8, 2005, the Board appointed the design-build firm of R.R. Simmons Construction Corporation to provide design and construction management services.

Change Orders No. 1 and 2 provide credits for the direct purchase of materials by the District. Change Order No. 3 provides a time extension to incorporate tenant improvement changes.

ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)

Goal 6 - All schools in the district will be assigned a state grade of A, B, or C.

FINANCIAL IMPACT (Budgeted: Yes)

This item is included in the District Capital Outlay: Land Proceeds and Certificates of Participation Series 04C.

Contract Status:
Guaranteed Maximum Price: $8,910,763.00
Change Order No. 1 Recommended Herein: $1,082,334.57 Credit
Change Order No. 2 Recommended Herein: $20,980.81 Credit
Change Order No. 3 Recommended Herein: $0.00 Extra
Revised Guaranteed Maximum Price: $7,807,447.62
Revised Construction Price: $8,847,772.89

Original Completion Date: May 25, 2007
Time Extension Recommended in Change Order No. 3: 21 Calendar Days
Revised Completion Date: June 15, 2007

EVALUATION

SUBMITTED BY:

J. Thomas Blackwell
General Manager of Construction
(813) 272-4112
Cathy L. Valdes
Chief Facilities Officer
(813) 272-4004
6.19