CLASSROOMS FOR KIDS (PACKAGE 3)
APPROVAL OF CHANGE ORDER NO. 1 - $185,094.25 EXTRA / 30 CALENDAR DAY TIME EXTENSION

EXECUTIVE SUMMARY

On September 7, 2004, the Board appointed Long & Associates and R.J. Bunbury Company, Inc. to provide design and construction management services for classroom additions at Crestwood, Egypt Lake, Mendenhall, and Tampa Bay Boulevard Elementary Schools. Roosevelt Elementary School was omitted due to budget and cost issues. The scope of work provides for the addition of 8 primary classrooms and replacement of the fire alarm and intercom systems throughout the existing facility.

This change order provides for removal and replacement of unsuitable soil. A time extension is included for completion of the work.

ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)

Goal 6 - All schools in the district will be assigned a state grade of A, B, or C.

FINANCIAL IMPACT (Budgeted: Yes)

This item is included in the District Capital Outlay: Classrooms for Kids.

Contract Status:
Guaranteed Maximum Price: $1,539,136.00
Change Order Recommended Herein: $185,094.25 Extra
Revised Guaranteed Maximum Price: $1,724,230.25
Revised Construction Cost: $1,724,230.25

Original Completion Date: May 16, 2007
Time Extension Recommended Herein: 30 Calendar Days
Revised Completion Date: June 15, 2007

EVALUATION

SUBMITTED BY:

J. Thomas Blackwell
General Manager of Construction
(813) 272-4112
Cathy L. Valdes
Chief Facilities Officer