Facilities Action Item |
DATE: Tuesday, February 13, 2007
TO: School Board Members
FROM: MaryEllen Elia, Superintendent
SUBJECT / RECOMMENDATIONS
EXECUTIVE SUMMARY
On January 17, 2006, the Board appointed The Architectural Practice, Inc. and Ellis Construction Company, Inc. to provide design and construction management services. This new facility is a reuse of the Collins Elementary School design. As of the current boundaries, relief will be provided for Bryant Elementary School.
The site work includes onsite and offsite utilities, paving, and earthwork required for the construction of the school.
Approval of Amendment No. 2 will permit construction of the site work. Project completion is scheduled for July 31, 2007.
ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)
FINANCIAL IMPACT (Budgeted: Yes)
Construction cost is warranted at $3,295,132. The construction budget is $3,295,132. This item is included in the District Capital Outlay: 2 Mill.
EVALUATION
SUBMITTED BY:
J. Thomas Blackwell
General Manager of Construction (813) 272-4112 |
Cathy L. Valdes
Chief Facilities Officer (813) 272-4004 |
6.10 | |
Hillsborough County Public Schools (Florida) * Mtg.#20070213_231 * Section E Item# 6.10 |