Facilities Action Item |
DATE: Tuesday, March 13, 2007
TO: School Board Members
FROM: MaryEllen Elia, Superintendent
SUBJECT / RECOMMENDATIONS
EXECUTIVE SUMMARY
On November 9, 2006, the Board appointed Long & Associates Architects/Engineers, Inc. and J.O. DeLotto & Sons, Inc. to provide design and construction management services. These additions are necessary to meet class size reduction requirements. The scope of work provides for the following additions: 16 classrooms at Bartels and 12 classrooms at Clark.
Approval of the schematic design phases will allow the architect to proceed with design development documents. Completion of each project is scheduled for July 2008.
ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)
FINANCIAL IMPACT (Budgeted: Yes)
The classroom additions are currently funded at $2,463,000 for Bartels Middle School and $1,848,000 for Clark Elementary School. The estimate of probable cost for each project is under review to identify design strategies to insure budget compliance. These items are included in the District Capital Outlay: Classrooms for Kids.
EVALUATION
SUBMITTED BY:
J. Thomas Blackwell
General Manager of Construction (813) 272-4112 |
Cathy L. Valdes
Chief Facilities Officer (813) 272-4004 |
6.10b | |
Hillsborough County Public Schools (Florida) * Mtg.#20070313_235 * Section E Item# 6.10b |