TINKER ELEMENTARY SCHOOL
DEMOLITION AND REPLACEMENT
APPROVAL OF CONSTRUCTION DOCUMENTS AND GUARANTEED MAXIMUM PRICE

EXECUTIVE SUMMARY

On March 8, 2005, the Board appointed the architectural firm of Gould Evans Associates with Manhattan Construction Company providing construction management services. The scope of work includes the demolition and replacement of the Administration, Media, and classroom buildings. Portables will be provided to house students and faculty until completion of the replacement facilities.

Approval of the guaranteed price will provide a maximum cost for the project. Project completion is scheduled for February 19, 2008.

ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)

Provide adequate school facilities for the accomplishment of all District Goals and Critical Success Factors.

FINANCIAL IMPACT (Budgeted: Yes)

Construction cost is warranted at $7,520,193. The construction budget is $7,520,193. This item is included in the District Capital Outlay: Community Investment Tax, Capital Outlay & Debt Service, and Classrooms for Kids.

EVALUATION

SUBMITTED BY:

J. Thomas Blackwell
General Manager of Construction
(813) 272-4112
Cathy L. Valdes
Chief Facilities Officer
(813) 272-4004