Facilities Action Item |
DATE: Tuesday, April 24, 2007
TO: School Board Members
FROM: MaryEllen Elia, Superintendent
SUBJECT / RECOMMENDATIONS
EXECUTIVE SUMMARY
RHC and Associates, Inc. and Kenyon & Partners, Inc. were selected from the Approved Continuing Services Consultants list to provide replacement of the heating, ventilating, and air conditioning (HVAC) system.
This change order provides credits for direct purchase of materials by the District and value engineering items deducted from the design documents. It also provides a new three way valve on the air handler.
ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)
Provide adequate school facilities for the accomplishment of all District Goals and Critical Success Factors.
FINANCIAL IMPACT (Budgeted: Yes)
This item is included in the District Capital Outlay: 2 Mill.
Contract Status:
Guaranteed Maximum Price: $727,495.00
Change Order Recommended Herein: $230,416.26 Credit and $5,665.00 Extra
Revised Guaranteed Maximum Price: $502,743.74
Revised Construction Cost: $662,514.74
Contract Completion Date: August 25, 2007
EVALUATION
SUBMITTED BY:
J. Thomas Blackwell
General Manager of Construction (813) 272-4112 |
Cathy L. Valdes
Chief Facilities Officer (813) 272-4004 |