RAMPELLO DOWNTOWN SCHOOL PARKING FACILITY
APPROVAL OF CHANGE ORDER NO. 2 - $522,212.83 NET CREDIT
ACCEPTANCE OF PROJECT

EXECUTIVE SUMMARY

On October 19, 2004, the Board appointed J.O. DeLotto & Sons, Inc. to provide design-build services for the Rampello Downtown School Parking Facility. The scope of work provided for construction of a new parking garage to house 450 automobiles.

This change order provides credits for deletion of cameras, project savings, return of unused contingency funds, and final reconciliation of the Direct Purchase Program. It also provides for water tie in, storm water revisions, storefront and awning, relocation of sanitary tie in and 6" water line, and modification of electrical service configuration.

ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)

Provide adequate school facilities for the accomplishment of all District Goals and Critical Success Factors.

FINANCIAL IMPACT (Budgeted: Yes)

This item is included in the District Capital Outlay: Community Investment Tax 2004.

Contract Status:
Guaranteed Maximum Price: $5,444,096.00
Change Order Previously Recommended: $18,422.00 Extra
Change Order Recommended Herein: $576,543.83 Credit and $54,331.00 Extra
Revised Guaranteed Maximum Price: $4,940,305.17
Payments to Date: $4,882,800.52
Balance Due: $57,504.65
Revised Construction Cost: $5,385,047.66

Original Completion Date: December 20, 2005
Time Extension Previously Approved: 97 Calendar Days
Revised Completion Date: March 27, 2006
Substantial Completion Date: March 27, 2006

EVALUATION

SUBMITTED BY:

J. Thomas Blackwell
General Manager of Construction
(813) 272-4112
Cathy L. Valdes
Chief Facilities Officer
(813) 272-4004
6.18
Hillsborough County Public Schools (Florida) * Mtg.#20070424_239 * Section E Item# 6.18