Facilities Action Item |
DATE: Tuesday, April 24, 2007
TO: School Board Members
FROM: MaryEllen Elia, Superintendent
SUBJECT / RECOMMENDATIONS
EXECUTIVE SUMMARY
On March 8, 2005, the board appointed Ruyle Hayes + Jennewein Architects P.A. and Construct Two Construction Managers, Inc. to provide design and construction management services for the addition of a gymnasium at Sligh Middle School.
This change order provides a time extension for permitting delays, Department of Education requirements, replacement of the existing chiller, and expansion of existing electrical service previously approved in Change Order No. 4.
ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)
Provide adequate school facilities for the accomplishment of all District Goals and Critical Success Factors.
FINANCIAL IMPACT (Budgeted: Yes)
This item is included in the District Capital Outlay: Certificates of Participation Series 2001B and 2 Mill.
Contract Status:
Guaranteed Maximum Price: $1,941,041.00
Change Orders Previously Approved: $517,681.54 Extra
Change Order Recommended Herein: $0.00 Extra
Revised Guaranteed Maximum Price: $2,458,722.54
Revised Construction Cost: $2,930,992.97
Original Completion Date: December 24, 2006
Time Extension Recommended Herein: 129 Calendar Days
Revised Completion Date: May 2, 2007
EVALUATION
SUBMITTED BY:
J. Thomas Blackwell
General Manager of Construction (813) 272-4112 |
Cathy L. Valdes
Chief Facilities Officer (813) 272-4004 |
6.16 | |
Hillsborough County Public Schools (Florida) * Mtg.#20070424_239 * Section E Item# 6.16 |