This project was planned by the engineering firm of Lyle Engineering Group, Inc. On February 7, 2006, the Board awarded the contract to the low bidder, Air Mechanical & Service Corp. The scope of work provides for replacement of the heating, ventilating, and air conditioning (HVAC) system.
This change order provides shut down relays for air handling units, air return ducts and power poles for compliance with code, installation of required pump disconnects, and replacement of inoperable control module and wiring. A time extension is included for completion of the work.
ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)
Provide adequate school facilities for the accomplishment of all District Goals and Critical Success Factors.
FINANCIAL IMPACT (Budgeted: Yes)
This item is included in the District Capital Outlay: 2 Mill.
Contract Status:
Contract Sum: $1,135,000.00
Change Order Previously Approved: $299,070.00 Credit
Change Order Recommended Herein: $28,489.98 Extra
Revised Contract Sum: $864,419.98
Revised Construction Cost: $1,146,419.98
Original Completion Date: August 1, 2006
Time Extension Recommended Herein: 90 Calendar Days
Revised Completion Date: October 30, 2006
EVALUATION
SUBMITTED BY:
J. Thomas Blackwell
General Manager of Construction (813) 272-4112 |
Cathy L. Valdes
Chief Facilities Officer (813) 272-4004 |
6.15 | |
Hillsborough County Public Schools (Florida) * Mtg.#20070424_239 * Section E Item# 6.15 |