EXECUTIVE SUMMARY
This project is being planned by the engineering firm of Carastro & Associates, Inc. The scope of work provides for demolition and replacement of the gymnasium lighting system. The project was advertised and bids received (see attachment). The low bidder, Riley Electric Company, Inc, is recommended. Project completion is scheduled for August 23, 2007.
ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)
Provide adequate school facilities for the accomplishment of all District Goals and Critical Success Factors.
FINANCIAL IMPACT (Budgeted: Yes)
Total funds in the amount of $43,762 are included in the District Capital Outlay: 2 Mill. The contract amount being awarded is $43,762.
EVALUATION
SUBMITTED BY:
Rory Salimbene
General Manager of Maintenance (813) 635-1101 |
Cathy L. Valdes
Chief Facilities Officer (813) 272-4004 |
6.05b | |