DURANT HIGH SCHOOL
CLASSROOM ADDITION
APPROVAL OF CHANGE ORDER NO. 1 - $45,266.95 EXTRA / 84 CALENDAR DAY TIME EXTENSION
APPROVAL OF CHANGE ORDER NO. 2 - $394,056.98 CREDIT
APPROVAL OF CHANGE ORDER NO. 3 - $7,435.00 EXTRA
APPROVAL OF CHANGE ORDER NO. 4 - $195,059.18 EXTRA / 30 CALENDAR DAY TIME EXTENSION

EXECUTIVE SUMMARY

On January 17, 2006, the Board appointed Reynolds, Smith & Hills, Inc. and Christiano Construction Company, Inc. to provide design and construction management services. The scope of work includes 24 new classrooms plus 2 student toilets, providing 600 additional student stations. This addition is necessary to meet class size reduction requirements.

Change Order No. 1 provides for a time extension and General Conditions necessitated by delay in project startup. Change Order No. 2 provides a credit for the direct purchase of materials by the District. Change Order No. 3 provides for modifications to the existing student emergency egress located at the west stairwell. Change Order No. 4 provides for increase in scope to retrofit the existing fire sprinkler system, provide a fire sprinkler system for new classroom addition, and related General Conditions. A time extension is included for completion of the work.

ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)

Provide adequate school facilities for the accomplishment of all District Goals and Critical Success Factors.

FINANCIAL IMPACT (Budgeted: Yes)

This item is included in the District Capital Outlay: Community Investment Tax 2006.
Contract Status:
Guaranteed Maximum Price: $3,574,049.00
Change Order No. 1 Recommended Herein: $45,266.95 Extra
Change Order No. 2 Recommended Herein: $394,056.98 Credit
Change Order No. 3 Recommended Herein: $7,435.00 Extra
Change Order No. 4 Recommended Herein: $195,059.18 Extra
Revised Guaranteed Maximum Price: $3,427,753.15
Revised Construction Cost: $3,798,986.15

Original Completion Date: August 13, 2007
Time Extension Recommended in Change Order No. 1: 84 Calendar Days
Time Extension Recommended in Change Order No. 4: 30 Calendar Days
Revised Completion Date: December 5, 2007

EVALUATION

SUBMITTED BY:

J. Thomas Blackwell
General Manager of Construction
(813) 272-4112
Cathy L. Valdes
Chief Facilities Officer
(813) 272-4004
6.10
Hillsborough County Public Schools (Florida) * Mtg.#20070508_241 * Section E Item# 6.10