Hillsborough County Public Schools Facilities
Action Item

DATE: Tuesday, May 8, 2007
TO: School Board Members
FROM: MaryEllen Elia, Superintendent

SUBJECT / RECOMMENDATIONS

REPLACEMENT OF FIRE ALARM AND/OR INTERCOM SYSTEMS AT VARIOUS SCHOOLS
AWARD OF CONTRACT

EXECUTIVE SUMMARY

This project is being planned by the engineering firm of KBA Engineering, Inc. The scope of work provides for replacement of the fire alarm and intercom systems at Bing and Hunter's Green Elementary Schools, Lincoln Magnet Elementary School, and Stewart Middle School, replacement of the intercom system at Robinson Elementary School, and replacement of the fire alarm system at Durant High School. The project was advertised and bids received (see attachment). The low bidder, Alarm & Communications Systems, Inc., is recommended. Project completion is scheduled for September 1, 2007. Provisions have been made for continuity of service of critical system functions during the project. The completed systems will be warranted for a period of five years.

ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)

Provide adequate school facilities for the accomplishment of all District Goals and Critical Success Factors.

FINANCIAL IMPACT (Budgeted: Yes)

Total funds in the amount of $1,256,070 are included in the District Capital Outlay: 2 Mill. The contract amount being awarded is $1,256,070.

EVALUATION

SUBMITTED BY:

Rory Salimbene
General Manager of Maintenance
(813) 635-1101
Cathy L. Valdes
Chief Facilities Officer
(813) 272-4004
6.04
Hillsborough County Public Schools (Florida) * Mtg.#20070508_241 * Section E Item# 6.04