EXECUTIVE SUMMARY
The existing Instructional Services Center had exceeded its useful life and was demolished to allow construction of a two-story 100,000 square foot office building. On March 8, 2005, the Board appointed the design-build firm of R.R. Simmons Construction Corporation to provide design and construction management services for the exterior building shell.
Change Order Nos. 4 and 5 provide credits for the direct purchase of materials by the District.
ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)
FINANCIAL IMPACT (Budgeted: Yes)
EVALUATION
SUBMITTED BY:
J. Thomas Blackwell
General Manager of Construction (813) 272-4112 |
Cathy L. Valdes
Chief Facilities Officer (813) 272-4004 |