This project was planned by the engineering firm of A.J. Sanchez Consulting Engineers, Inc. On April 4, 2006, the Board awarded the project to the only bidder, Air Mechanical & Service Corp. The scope of work provides for replacement of the heating, ventilating, and air conditioning (HVAC) system.
This change order provides for work originally deleted from the scope in Deductive Alternate No. 7. The amount was adjusted to reflect a deduction from Carroll Air for the cost of the air handlers. A time extension is included for completion of the work.
ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)
Provide adequate school facilities for the accomplishment of all District Goals and Critical Success Factors.
FINANCIAL IMPACT (Budgeted: Yes)
EVALUATION
SUBMITTED BY:
J. Thomas Blackwell
General Manager of Construction (813) 272-4112 |
Cathy L. Valdes
Chief Facilities Officer (813) 274-4004 |