Hillsborough County Public Schools Facilities
Action Item

DATE: Tuesday, June 12, 2007
TO: School Board Members
FROM: MaryEllen Elia, Superintendent

SUBJECT / RECOMMENDATIONS

DURANT HIGH SCHOOL
CLASSROOM ADDITION
APPROVAL OF CHANGE ORDER NO. 5 - $51,886.63 CREDIT

EXECUTIVE SUMMARY

On January 17, 2006, the Board appointed Reynolds, Smith & Hills, Inc. and Christiano Construction Company, Inc. to provide design and construction management services. The scope of work includes 24 new classrooms plus 2 student toilets, providing 600 additional student stations. This addition is necessary to meet class size reduction requirements.

This change order provides a credit for the direct purchase of materials by the District.

ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)

Provide adequate school facilities for the accomplishment of all District Goals and Critical Success Factors.

FINANCIAL IMPACT (Budgeted: Yes)

This item is included in the District Capital Outlay: Community Investment Tax 2006.

Contract Status:
Guaranteed Maximum Price: $3,574,049.00
Change Orders Previously Approved: $146,295.85 Credit
Change Order Recommended Herein: $51,886.63 Credit
Revised Guaranteed Maximum Price: $3,375,866.52
Revised Construction Cost: $3,795,954.83

Original Completion Date: August 13, 2007
Time Extensions Previously Approved: 114 Calendar Days
Revised Completion Date: December 5, 2007

EVALUATION

SUBMITTED BY: Alice Sutton, Project Coordinator



Cathy L. Valdes
Chief Facilities Officer
(813) 272-4004
6.08
Hillsborough County Public Schools (Florida) * Mtg.#20070612_246 * Section E Item# 6.08