Hillsborough County Public Schools Facilities
Action Item

DATE: Tuesday, June 12, 2007
TO: School Board Members
FROM: MaryEllen Elia, Superintendent

SUBJECT / RECOMMENDATIONS

ORANGE GROVE MIDDLE SCHOOL
RENOVATION
APPROVAL OF CONSTRUCTION DOCUMENTS AND GUARANTEED MAXIMUM PRICE

EXECUTIVE SUMMARY

This project is being planned by the architectural firm of Atelier AEC, Inc. On January 16, 2007, the Board appointed the construction management firm of Walbridge Aldinger Co. The scope of renovation provides for new finishes throughout the facility, restoration of wood flooring, replacement of lighting, interior stairs, and heating, ventilating, and air conditioning (HVAC) system, upgrades to intercom, data, and security systems, and toilet facilities to provide Americans with Disabilities (ADA) accessibility. Exterior work includes cleaning, repointing, and sealing of all brick work, new cafeteria patio cover, and roof replacement for the classroom building, cafeteria and second story walkways.

Approval of the guaranteed price will provide a maximum cost for the facility. Project completion is scheduled for June 12, 2008.

ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)

Provide adequate school facilities for the accomplishment of all District Goals and Critical Success Factors.

FINANCIAL IMPACT (Budgeted: Yes)

Construction cost is warranted at $3,496,000. The construction budget is $3,496,000. This item is included in the District Capital Outlay: 2 Mill.

EVALUATION

SUBMITTED BY: John Williams, Project Coordinator



Cathy L. Valdes
Chief Facilities Officer
(813) 272-4004
6.04c
Hillsborough County Public Schools (Florida) * Mtg.#20070612_246 * Section E Item# 6.04c