EXECUTIVE SUMMARY
On January 17, 2006, the Board appointed The Architectural Practice, Inc. and Ellis Construction Company, Inc. to provide design and construction management services. This new facility is a reuse of the Collins Elementary School design. As of the current boundaries, relief will be provided for Bryant Elementary School.
This change order provides a credit for the direct purchase of materials by the District.
ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)
FINANCIAL IMPACT (Budgeted: Yes)
This item is included in the District Capital Outlay: Certificates of Participation Series 2004C, Classrooms for Kids 2005, Community Investment Tax, and School Infrastructure Thrift Award.
Contract Status:
Guaranteed Maximum Price: $13,003,371.00
Change Order Previously Approved: $2,981,668.07 Credit
Change Order Recommended Herein: $822,026.99 Credit
Revised Guaranteed Maximum Price: $9,199,675.94
Revised Construction Cost: $12,786,065.65
Contract Completion Date: July 31, 2007
EVALUATION
SUBMITTED BY: Alice Sutton, Project Coordinator
|
Cathy L. Valdes
Chief Facilities Officer (813) 272-4004 |