Facilities Action Item |
DATE: Tuesday, June 12, 2007
TO: School Board Members
FROM: MaryEllen Elia, Superintendent
SUBJECT / RECOMMENDATIONS
EXECUTIVE SUMMARY
On January 17, 2006, the Board appointed The Architectural Practice, Inc. and Ellis Construction Company, Inc. to provide design and construction management services. This new facility is a reuse of the Collins Elementary School design. As of the current boundaries, relief will be provided for Bryant Elementary School.
The site work includes onsite and offsite utilities, paving, and earthwork required for the construction of the school.
Change Order No. 2 provides for revisions to landscaping and irrigation at the north property boundary to improve the neighboring homes buffer. Change Order No. 3 provides a credit for the direct purchase of materials by the District.
ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)
FINANCIAL IMPACT (Budgeted: Yes)
EVALUATION
SUBMITTED BY: Alice Sutton, Project Coordinator
|
Cathy L. Valdes
Chief Facilities Officer (813) 272-4004 |
6.11 | |
Hillsborough County Public Schools (Florida) * Mtg.#20070612_246 * Section E Item# 6.11 |