APPROVAL OF CHANGE ORDER NO. 7 - $26,919.00 NET EXTRA

EXECUTIVE SUMMARY

This project was planned by the architectural firm of The Architectural Practice, Inc. On May 16, 2006, the Board awarded the contract for construction management services to Ellis Construction Company, Inc. The scope of work provides for a new 720 student station elementary school.

This change order provides for cell tower revisions, modifications to range hood exhaust and the 46th Street entrance drive, stainless steel tube for kitchen hood, black vinyl fence, additional curb, epoxy paint in kitchen, and relocation of fire alarm strobes. Also included are credits for high abuse drywall in lieu of fiberock, and deletion of storm sewer section and stage curtain valance.

ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)

Provide adequate school facilities for the accomplishment of all District Goals and Critical Success Factors.

FINANCIAL IMPACT (Budgeted: Yes)

This item is included in the District Capital Outlay: Certificates of Participation Series 2004C, Classrooms for Kids 2005, and School Infrastructure Thrift Award (SIT).

Contract Status:
Contract Sum: $10,911,792.00
Change Orders Previously Approved: $3,071,009.82 Credit
Change Order Recommended Herein: $32,093.00 Extra and $5,174.00 Credit
Revised Contract Sum: $7,867,701.18
Revised Construction Cost: $10,992,705.82

Contract Completion Date: May 10, 2007

EVALUATION

SUBMITTED BY:

J. Thomas Blackwell
General Manager of Construction
(813) 272-4112
Cathy L. Valdes
Chief Facilities Officer
(813) 272-4004
6.18
Hillsborough County Public Schools (Florida) * Mtg.#20070717_261 * Section E Item# 6.18