Facilities Action Item |
DATE: Tuesday, July 17, 2007
TO: School Board Members
FROM: MaryEllen Elia, Superintendent
SUBJECT / RECOMMENDATIONS
EXECUTIVE SUMMARY
On November 9, 2006, the Board appointed Holmes Hepner and Associates Architects and The Morganti Group, Inc. to provide design and construction management services for classroom additions at various schools. The architectural agreement for the classroom additions at Burnett Middle School, Riverview High School, Rodgers Middle School, and Wharton High School and the construction management agreement for the classroom additions at Collins Elementary School, Riverview High School, Rodgers Middle School, and Summerfield Elementary School are being amended to include the summer painting project at Riverview High School. The scope of work includes repainting of exterior and interior of school.
Approval of the guaranteed price will provide a maximum cost for the project. Completion is scheduled for August 24, 2007.
ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)
FINANCIAL IMPACT (Budgeted: Yes)
EVALUATION
SUBMITTED BY:
J. Thomas Blackwell
General Manager of Construction (813) 272-4112 |
Cathy L. Valdes
Chief Facilities Officer (813) 272-4004 |
6.14 | |