Facilities Action Item |
DATE: Tuesday, July 31, 2007
TO: School Board Members
FROM: MaryEllen Elia, Superintendent
SUBJECT / RECOMMENDATIONS
EXECUTIVE SUMMARY
This project was planned by the architectural firm of Sylla, Inc. On November 18, 2003, the Board appointed the construction management firm of HCBeck, Ltd. This new facility, which opened in August 2006, was a reuse of the Middleton High School design and relieved overcrowding at East Bay, Riverview, and Bloomingdale High Schools.
Change Order No. 10 provides for final reconciliation of the Owner Controlled Insurance Program. Change Order No. 11 provides for final reconciliation of the Direct Purchase Program.
ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)
Provide adequate school facilities for the accomplishment of all District Goals and Critical Success Factors.
FINANCIAL IMPACT (Budgeted: Yes)
This item is included in the District Capital Outlay: Certificates of Participation Series 2003 (new facility), and Certificates of Participation Series 1999 (athletic facility).
Contract Status:
Guaranteed Maximum Price: $33,178,803.00
Change Orders Previously Approved: $7,968,684.07 Credit
Change Order No. 10 Recommended Herein: $50,718.88 Extra
Change Order No. 11 Recommended Herein: $57,555.50 Credit
Revised Guaranteed Maximum Price: $25,203,282.31
Revised Construction Cost: $33,920,358.62
Original Completion Date: November 18, 2005
Time Extension Previously Approved: 223 Calendar Days
Revised Completion Date: June 29, 2006
EVALUATION
SUBMITTED BY:
J. Thomas Blackwell
General Manager of Construction (813) 272-4112 |
Cathy L. Valdes
Chief Facilities Officer (813) 272-4004 |
6.06 | |
Hillsborough County Public Schools (Florida) * Mtg.#20070731_262 * Section E Item# 6.06 |