EXECUTIVE SUMMARY

On March 8, 2005, the Board appointed the architectural firm of Gould Evans Associates with Manhattan Construction Company providing construction management services. The scope of work includes the demolition and replacement of the Administration, Media, and classroom buildings. Portables have been provided to house students and faculty until completion of the replacement facilities.

This change order provides a credit for the direct purchase of materials by the District.

ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)

Provide adequate school facilities for the accomplishment of all District Goals and Critical Success Factors.

FINANCIAL IMPACT (Budgeted: Yes)

This item is included in the District Capital Outlay: Community Investment Tax, Capital Outlay & Debt Service, and Classrooms for Kids.

Contract Status:
Guaranteed Maximum Price: $7,520,193.00
Change Order Previously Approved: $55,745.77 Extra
Change Order Recommended Herein: $808,865.67 Credit
Revised Guaranteed Maximum Price: $6,767,073.10
Revised Construction Cost: $7,531,501.25

Contract Completion Date: February 19, 2008

EVALUATION

SUBMITTED BY:

J. Thomas Blackwell
General Manager of Construction
(813) 272-4112
Cathy L. Valdes
Chief Facilities Officer
(813) 272-4004
6.08
Hillsborough County Public Schools (Florida) * Mtg.#20070906_278 * Section E Item# 6.08