Hillsborough County Public Schools Facilities
Action Item

DATE: Tuesday, June 7, 2005
TO: School Board Members
FROM: Earl J. Lennard, Superintendent

SUBJECT / RECOMMENDATIONS

ADAMS MIDDLE SCHOOL - ADDITION AND RENOVATE
APPROVAL OF CHANGE ORDER NO. 5 - $1,691,997.66 NET CREDIT / 42 CALENDAR DAY TIME EXTENSION

EXECUTIVE SUMMARY

This project was planned by the architectural firm of Ruyle and Masters + Jennewein Architects, P.A. On March 12, 2002, the Board appointed the construction management firm of Bovis Lend Lease. The scope of work includes the addition of a gymnasium, conversion of locker rooms in Building 5 into four classrooms, reflashing and reroofing of Buildings 1, 2, 3, 4, 5, and the canopies east and west of Building 3, replacement of all windows in Buildings 1, 3, 4, 5 and 6, replacement of hot water heating with electric heating, and replacement of air conditioning units in Buildings 3, 4, 5 and 6. Renovation of Buildings 1, 3, 4, 5, and 6 will include painting and replacement of floors, ceilings and lighting. Restrooms will be renovated to meet code requirements. New fire alarm, intercom, telephone, security and data network systems will be installed. In Building 4 corridor, the clerestory windows will be replaced with a one-hour rated infill, and modifications will be made to make the corridor walls on the second level of Building 3 one-hour rated to meet fire code. The wheel chair lift will be replaced with an elevator, and balcony handrails will be replaced on Building 3. Minor drainage issues will be corrected throughout the facility.

This change order provides credits for project savings, the return of unused contingency funds, and final reconcilation of the Direct Purchase and Owner Controlled Insurance Programs. It also provides for the remediation of exterior walkways and corridors in Building 3 to prevent rain water intrusion at doorways. A time extension is provided for the additional scope of work added in Change Orders 1 through 4 which included the removal and replacement of all exterior walls in Buildings 1 through 6.

ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)

Critical Success Factor 6.a.8 - Provide sufficient student stations to ensure uninterrupted student learning and data gathering as measured by District Operations Goals plan.

FINANCIAL IMPACT (Budgeted: Yes)

This item is included in the District Capital Outlay: Community Investment Tax.
Contract Status:
Guaranteed Maximum Price: $6,426,167.00
Previously Approved: $599,715.00 Extra
Recommended Herein: $1,720,603.44 Credit and $28,605.78 Extra
Revised Guaranteed Maximum Price: $5,333,884.34
Original Completion Date: July 30, 2004
Time Extension Requested Herein: 42 Calendar Days
Revised Completion Date: September 10, 2004

EVALUATION

SUBMITTED BY:

J. Thomas Blackwell
General Manager of Construction
(813) 272-4112
MaryEllen Elia
Chief Facilities Officer
(813) 272-4004
6.17
Hillsborough County Public Schools (Florida) * Mtg.#20050607_144 * Section E Item# 6.17