Facilities Action Item |
DATE: Tuesday, June 7, 2005
TO: School Board Members
FROM: Earl J. Lennard, Superintendent
SUBJECT / RECOMMENDATIONS
EXECUTIVE SUMMARY
This project was planned by the architectural firm of Howard and Associates, Architects, PA. On March 12, 2002, the Board appointed the construction management firm of The Morganti Group. The scope of work includes the addition of a new gymnasium and elevator. Also included is the renovation of existing classrooms, administration offices, and the auditorium to accommodate the new magnet program.
This change order provides credits to the Direct Purchase and Owner Controlled Insurance Programs.ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)
Critical Success Factor 6.a.8 - Provide sufficient student stations to ensure uninterrupted student learning and data gathering as measured by District Operational Goals plan.
FINANCIAL IMPACT (Budgeted: Yes)
This item is included in the District Capital Outlay: Community Investment Tax and 2 Mill.
Contract Status:
Guaranteed Maximum Price: $4,600,000.00
Change Orders Previously Approved: $2,835,810.90 Extra
Change Order No. 5 Recommended Herein: $914,262.24 Credit
Revised Guaranteed Maximum Price: $6,521,548.66
Original Completion Date: September 1, 2004
Time Extension Previously Approved: 316 Calendar Days
Revised Completion Date: July 14, 2005
EVALUATION
SUBMITTED BY:
J. Thomas Blackwell
General Manager of Construction (813) 272-4112 |
MaryEllen Elia
Chief Facilities Officer (813) 272-4004 |
6.10 | |
Hillsborough County Public Schools (Florida) * Mtg.#20050607_144 * Section E Item# 6.10 |