Hillsborough County Public Schools Facilities
Action Item

DATE: Tuesday, July 12, 2005
TO: School Board Members
FROM: MaryEllen Elia, Superintendent

SUBJECT / RECOMMENDATIONS

GORRIE ELEMENTARY SCHOOL
HISTORIC RENOVATIONS
APPROVAL OF CONSTRUCTION DOCUMENTS AND GUARANTEED MAXIMUM PRICE

EXECUTIVE SUMMARY

This project is being planned by the architectural firm of Robbins, Bell & Kreher Architects. On May 1, 2001, the Board appointed the construction management firm of Kalemeris Construction, Inc. The scope of work includes new doors and windows at the front entry, two new fire-rated windows in Building 2, and the replacement of two existing windows with new fire-rated windows in Building 4.

Approval of the guaranteed price will provide a maximum cost for the project. Completion is scheduled for September 20, 2005.

ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)

Critical Success Factor 6.a8 - Provide sufficient student stations to ensure uninterrupted student learning and data gathering as measured by District Operational Goals plan.

FINANCIAL IMPACT (Budgeted: Yes)

Construction cost is warranted at $184,330. The construction budget is $211,114. Funding is being provided by a grant from the State of Florida Department of Historical Resources.

EVALUATION

SUBMITTED BY:

J. Thomas Blackwell
General Manager of Construction
(813) 272-4112
James Hamilton
Chief of Staff
(813) 272-4101
6.07c
Hillsborough County Public Schools (Florida) * Mtg.#20050712_146 * Section E Item# 6.07c