Hillsborough County Public Schools Facilities
Action Item

DATE: Tuesday, July 26, 2005
TO: School Board Members
FROM: MaryEllen Elia, Superintendent

SUBJECT / RECOMMENDATIONS

HIGH SCHOOL “RRR” (SOUTH SHORE)
NEW FACILITY
APPROVAL OF CHANGE ORDER NO. 1 - $6,295,949.61 CREDIT

EXECUTIVE SUMMARY

This project was planned by the architectural firm of Holmes Hepner & Associates Architects. On June 15, 2004, the Board appointed the construction management firm of the Beck Group. This new facility will be a reuse of the Alonso High School design. As of the current boundaries, relief will be provided for East Bay High School and the South County area.

This change order provides a credit for the direct purchase of materials by the District.

ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)

Critical Success Factor 6.a.8 - Provide sufficient student stations to ensure uninterrupted student learning and data gathering as measured by District Operational Goals plan.

FINANCIAL IMPACT (Budgeted: Yes)

This item is included in the District Capital Outlay: Community Investment Tax 2004 (new facility) and Certificates of Participation Series 2004C (athletic facility).

Contract Status:
Guaranteed Maximum Price: $35,159,855.00
Change Order Recommended Herein: $6,295,949.61 Credit
Revised Guaranteed Maximum Price: $28,863,905.39

Contract Completion Date: July 24, 2006

EVALUATION

SUBMITTED BY:

J. Thomas Blackwell
General Manager of Construction
(813) 272-4102
Cathy L. Valdes
Chief Facilities Officer
(813) 272-4004
6.06
Hillsborough County Public Schools (Florida) * Mtg.#20050726_148 * Section E Item# 6.06