Facilities Action Item |
DATE: Tuesday, April 20, 2010
TO: School Board Members
FROM: MaryEllen Elia, Superintendent
SUBJECT / RECOMMENDATIONS
EXECUTIVE SUMMARY
Carastro & Associates, Inc. was selected from the approved Continuing Services Consultants list to provide design services. On May 19, 2009, the contract for construction was awarded to the low bidder, B & I Contractors, Inc. The scope of work provided for replacement of selected HVAC equipment at Burney, Clair Mel, Foster, Mendenhall and Riverview Elementary Schools, and Greco Middle School. The Board had previously approved the purchase of major equipment for the project.
This change order provides a credit for the return of unused contingency funds.
The engineer advises that the referenced project is finally complete in accordance with the plans and specifications and other contract documents and recommends Board acceptance.
ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)
FINANCIAL IMPACT (Budgeted: Yes)
EVALUATION
SUBMITTED BY: Eugene Runnels, Project Coordinator
Rory Salimbene
General Manager of Construction (813) 272-4112 |
Daniel J. Valdez
Deputy Superintendent (813) 272-4166 |
A 6.11 | |
Hillsborough County Public Schools (Florida) * Mtg.#20100420_398 * Section A Item# 6.11 |