Hillsborough County Public Schools Facilities
Action Item

DATE: Tuesday, May 18, 2010
TO: School Board Members
FROM: MaryEllen Elia, Superintendent

SUBJECT / RECOMMENDATIONS

Approve Award of Contract for Heating, Ventilating, and Air Conditioning (HVAC) Renovation at
Tampa Palms Elementary School

EXECUTIVE SUMMARY

On November 3, 2009, the Board appointed the engineering firm of Lyle Engineering Group, Inc. to provide design services. The scope of work provides for renovation of the HVAC system throughout the campus and includes replacement of the existing cooling plant with a thermal ice storage system; new air handlers and ductwork; and a new energy management system. The project scope also includes replacement of ceilings and lights throughout the majority of the campus, and new intercom and fire alarm systems. The Board has previously approved the purchase of major equipment for the project.

The project was advertised and bids received (see attachment). Award of the contract as indicated on the attachment for the base bid and alternates to the lowest qualified bidder, Walbridge Aldinger Company, is recommended.

ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)

* Construct and maintain facilities that create an environment conducive to teaching and learning

FINANCIAL IMPACT (Budgeted: Yes)

Total funds in the amount of $2,500,000 are included in the District Capital Outlay: Local Millage. The contract amount being awarded is $2,484,000.

EVALUATION

SUBMITTED BY: Ellis Curry, Project Coordinator

Rory Salimbene
General Manager of Construction
(813) 272-4112
Daniel J. Valdez
Deputy Superintendent
(813) 272-4166
A 6.05g
Hillsborough County Public Schools (Florida) * Mtg.#20100518_401 * Section A Item# 6.05g