Hillsborough County Public Schools Facilities
Action Item

DATE: Tuesday, June 15, 2010
TO: School Board Members
FROM: MaryEllen Elia, Superintendent

SUBJECT / RECOMMENDATIONS

Approve Acceptance of Project for Classrooms for Kids Addition at
Collins Elementary School

EXECUTIVE SUMMARY

On November 9, 2006, the Board appointed The Architectural Practice, Inc. and The Morganti Group, Inc. to provide design and construction management services. The scope of work provided for an additional 14 classrooms. This addition was necessary to meet class size reduction requirements.

The architect advises that the referenced project is finally complete in accordance with the plans and specifications and other contract documents and recommends Board acceptance.

ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)

* Construct and maintain facilities that create an environment conducive to teaching and learning

FINANCIAL IMPACT (Budgeted: Yes)

This item was included in the District Capital Outlay: Classrooms for Kids.

Contract Status:
Guaranteed Maximum Price: $2,571,073.00
Approved Change Orders: $562,315.17 Credit (See Attachment)
Revised Guaranteed Maximum Price: $2,008,757.83
Payments to Date: $1,997,452.58
Balance: $11,305.25
Revised Construction Cost: $2,490,885.58

Contract Completion Date: August 4, 2008
Substantial Completion Date: October 6, 2008

EVALUATION

SUBMITTED BY: Ellis Curry, Project Coordinator

Rory Salimbene
General Manager of Construction
(813) 272-4112
Cathy L. Valdes
Chief Facilities Officer
(813) 272-4004
A 6.13b
Hillsborough County Public Schools (Florida) * Mtg.#20100615_402 * Section A Item# 6.13b