Facilities Action Item |
DATE: Tuesday, June 15, 2010
TO: School Board Members
FROM: MaryEllen Elia, Superintendent
SUBJECT / RECOMMENDATIONS
EXECUTIVE SUMMARY
The Architectural Practice, Inc. and J.B.D. Construction, Inc. were selected from the approved Continuing Services Consultants list to provide design and construction management services. The scope of work provides for removal and replacement of specific areas of steel deck, roof edge, and related components, and removal and replacement of soffit materials on Building 1 (classroom) and Building 2 (gymnasium).
Approval of the guaranteed maximum price will establish the cost for the project.
ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)
FINANCIAL IMPACT (Budgeted: Yes)
Construction cost is warranted at $162,000. The construction budget is $165,000. This item is included in the District Capital Outlay: Local Millage.
EVALUATION
SUBMITTED BY: Alice Sutton, Project Coordinator
Rory Salimbene
General Manager of Construction (813) 272-4112 |
Cathy L. Valdes
Chief Facilities Officer (813) 272-4004 |
A 6.11c | |
Hillsborough County Public Schools (Florida) * Mtg.#20100615_402 * Section A Item# 6.11c |